建筑實操,超高層施工技術一鍵掌握
超高(gao)(gao)層(ceng)(ceng)(ceng)(ceng)建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)指(zhi)40層(ceng)(ceng)(ceng)(ceng)以(yi)(yi)上(shang),高(gao)(gao)度100m以(yi)(yi)上(shang)的建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)物。建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)高(gao)(gao)度超過(guo)100m時,不論住宅(zhai)及公共建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)均為(wei)(wei)超高(gao)(gao)層(ceng)(ceng)(ceng)(ceng)建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)。根(gen)據世界(jie)超高(gao)(gao)層(ceng)(ceng)(ceng)(ceng)建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)學會的新標準,300m以(yi)(yi)上(shang)為(wei)(wei)超高(gao)(gao)層(ceng)(ceng)(ceng)(ceng)建(jian)(jian)(jian)筑(zhu)(zhu)(zhu)。
地下工(gong)程施工(gong)
1、降低地(di)下(xia)水位
降(jiang)(jiang)低地(di)(di)(di)下水(shui)方案(an)有深(shen)(shen)井(jing)(jing)降(jiang)(jiang)水(shui)和(he)井(jing)(jing)點降(jiang)(jiang)水(shui)2種。深(shen)(shen)井(jing)(jing)降(jiang)(jiang)水(shui)方案(an)費用偏高,但其(qi)施(shi)工(gong)(gong)可與打(da)樁(zhuang)平行進行;而井(jing)(jing)點降(jiang)(jiang)水(shui)方案(an)在(zai)埋設(she)井(jing)(jing)管(guan)時不能打(da)樁(zhuang),將使總工(gong)(gong)期(qi)拖(tuo)延60d。此外,深(shen)(shen)井(jing)(jing)抽出(chu)的(de)地(di)(di)(di)下水(shui),可用于(yu)沖洗骨料和(he)養護(hu)混凝(ning)土,可降(jiang)(jiang)低夏(xia)季混凝(ning)土的(de)施(shi)工(gong)(gong)溫度。在(zai)基坑開挖(wa)前要(yao)做好排除(chu)地(di)(di)(di)下水(shui)的(de)相應設(she)施(shi),在(zai)基坑四周挖(wa)好排水(shui)溝和(he)集水(shui)井(jing)(jing),保證基坑干燥(zao)。
2、塔樓浮(fu)筏基礎施工
塔樓浮筏基(ji)礎(chu)呈正方形(xing),將筏基(ji)在豎向上分(fen)為I和(he)II 2個(ge)施工層,每層連續(xu)澆筑,不(bu)留施工縫。
(1)筏基模板
外模(mo)采用MU7.5紅磚、M5砂(sha)漿砌筑的磚模(mo),厚(hou)度分別為240mm和370mm,內表面抹20mm水泥砂(sha)漿,采用普通木(mu)模(mo)板。
(2)筏基(ji)鋼筋
按施(shi)(shi)工圖和施(shi)(shi)工驗收規(gui)范要求施(shi)(shi)工,為保證筏(fa)基上層鋼筋的正確(que)位置(zhi),采(cai)用角鋼支架(jia)固定。
(3)筏(fa)基混凝土(tu)
由于混(hun)凝(ning)土澆筑量大(da),選用攪(jiao)拌站集中攪(jiao)拌和泵送混(hun)凝(ning)土;在(zai)施(shi)工層I與II間的施(shi)工縫,采用留齒槽和鋼(gang)板止水帶(dai),其外壁采用進口(kou)合成橡膠(jiao)止水帶(dai)。
3、地下室柱(zhu)和墻板(ban)施工
采(cai)用木模板(ban)經(jing)計算和實(shi)測(ce),按(an)4.75m澆筑高度(du),地下室頂(ding)板(ban)采(cai)用定型模板(ban)。模板(ban)和鋼筋運輸(shu),由(you)設(she)在基坑邊的塔式(shi)和輪胎式(shi)起重機(ji)完(wan)成。混(hun)凝土由(you)泵輸(shu)送(song),采(cai)用插入式(shi)和平板(ban)振搗器搗實(shi),并要及時養護(hu)。
非標準(zhun)層施工(gong)
1、垂直運輸機械
垂直運輸(shu)機械(xie)的選擇通(tong)過(guo)計算(suan)工(gong)作幅度、起重(zhong)高度、起重(zhong)量和起重(zhong)力(li)矩等主要(yao)參數及塔式起重(zhong)機的生產率等,進行綜合考慮,擇優選用。布置(zhi)方案如下。
(1)在塔樓南側設1臺S2348-2?C型定點(dian)塔式起重機,機高(gao)110m,起重能力為100t·m。
(2)在(zai)塔樓西部(bu)設雙籠施工(gong)電梯1臺,負責(ze)人員、小(xiao)型工(gong)具和零星材料的垂直運(yun)輸。
(3)在中心(xin)筒(tong)內設4臺(tai)1.6m×1.6m附墻金屬(shu)井架(jia),并以角鋼做斜撐(cheng)聯(lian)成(cheng)整(zheng)體,不另設纜風(feng)繩(sheng),井架(jia)總保持高于施工(gong)樓層(ceng)12m。負(fu)責模板、材料及工(gong)具運輸,并作為混(hun)凝(ning)土泵故障時(shi)的應急(ji)運輸設備。
(4)在塔(ta)樓外側設BP550·HDD-15型混(hun)凝土輸(shu)送泵1臺,負責混(hun)凝土垂直和(he)水平(ping)運輸(shu)。
(5)裙樓設3臺起重能力為45t·m的(de)塔式起重機,負責該(gai)樓的(de)水(shui)平和(he)垂直(zhi)運輸。
2、腳手(shou)架
為便(bian)于裙樓和塔樓安裝模板(ban)、綁扎(zha)鋼(gang)筋和外裝飾,均采用雙排鋼(gang)管外腳(jiao)(jiao)手架(jia)。裙樓外腳(jiao)(jiao)手架(jia)高約11m;塔樓每7層從窗口挑(tiao)出槽鋼(gang)進行搭(da)設,并與塔樓臨時固(gu)定。
標準層(ceng)施工
1、標準層(ceng)模板
模(mo)板(ban)工(gong)程(cheng)的設計,首(shou)先是確(que)定模(mo)板(ban)形式,然后(hou)進(jin)行底模(mo)、側模(mo)和(he)支撐系統(tong)驗算(suan),確(que)保工(gong)程(cheng)質(zhi)量。在(zai)(zai)塔樓標準層施工(gong)時,一(yi)次制(zhi)作4層模(mo)板(ban),柱、墻和(he)梁均為(wei)定型模(mo)板(ban),高度為(wei)2.55m,面板(ban)采(cai)用(yong)九(jiu)夾板(ban),以(yi)木(mu)(mu)螺絲固(gu)定于木(mu)(mu)制(zhi)立(li)帶上(shang),其構造設計同地下室(shi)模(mo)板(ban)。外柱和(he)4個(ge)角筒外模(mo),其安裝垂直度要用(yong)經緯儀校(xiao)核,每層控(kong)制(zhi)偏差在(zai)(zai)5mm以(yi)內,上(shang)下層模(mo)板(ban)的支柱應(ying)在(zai)(zai)同一(yi)條中心線上(shang)。
2、標準層鋼筋
塔樓標(biao)準層鋼筋(jin),在地面(mian)綁扎成(cheng)型或焊接成(cheng)骨架(jia)和網片,然后成(cheng)組安(an)裝(zhuang),以減少高空作業(ye)量。
3、標準層混凝土
每層混凝(ning)土量均在266~297m3之(zhi)間;須(xu)加強混凝(ning)土攪拌站和(he)輸送泵(beng)的管理;盡量避免壓送混凝(ning)土時出(chu)現中(zhong)斷。
裝飾工(gong)程(cheng)施工(gong)
1、裝飾工程工藝
全(quan)部(bu)內外高級裝飾,須先做出一(yi)個(ge)樣(yang)板(ban),經質(zhi)量和(he)色彩驗收合(he)格后(hou),方可全(quan)面(mian)施工(gong)。在裝飾工(gong)程階(jie)段(duan),組(zu)(zu)建(jian)抹灰(hui)、木裝修和(he)油漆等(deng)(deng)3個(ge)專(zhuan)業工(gong)作隊(dui),組(zu)(zu)建(jian)鋼窗、壁紙(zhi)、貼瓷(ci)磚和(he)鋪地(di)毯(tan)等(deng)(deng)專(zhuan)業班組(zu)(zu),全(quan)部(bu)專(zhuan)業隊(dui)組(zu)(zu)。
裙樓主(zhu)體完(wan)成(cheng)后,自(zi)上(shang)而(er)(er)下逐層(ceng)(ceng)、逐間進(jin)行(xing)內裝飾(shi),同(tong)(tong)層(ceng)(ceng)內按(an)天棚、墻面和(he)地面順序施工(gong)。而(er)(er)塔樓主(zhu)體完(wan)成(cheng)5層(ceng)(ceng)以后,開始(shi)內裝飾(shi)。主(zhu)體全部完(wan)成(cheng)后,以每10層(ceng)(ceng)為一個(ge)施工(gong)段(duan),自(zi)上(shang)而(er)(er)下進(jin)行(xing)流水施工(gong),在(zai)同(tong)(tong)層(ceng)(ceng)內按(an)照衛生(sheng)間、臥室和(he)走廊(lang)的順序施工(gong)。外裝飾(shi)也采取自(zi)上(shang)而(er)(er)下、以每10層(ceng)(ceng)為一個(ge)施工(gong)段(duan),逐段(duan)逐層(ceng)(ceng)進(jin)行(xing)施工(gong)。
2、腳手架和垂直運輸
地下室、裙樓(lou)和(he)塔樓(lou)非標準層(ceng)的(de)內裝(zhuang)飾,均采用(yong)(yong)鋼管滿堂紅腳(jiao)手架(jia);塔樓(lou)標準層(ceng),采用(yong)(yong)輕便式工(gong)(gong)具腳(jiao)手架(jia);外裝(zhuang)飾全部采用(yong)(yong)進(jin)口吊(diao)籃。裙樓(lou)用(yong)(yong)3臺金屬井架(jia),塔樓(lou)用(yong)(yong)電梯井內的(de)4臺井架(jia)和(he)外墻施工(gong)(gong)的(de)電梯,分(fen)別作為垂直運輸(shu)工(gong)(gong)具。
混(hun)凝土施工
(1)核心筒超厚墻體高強度(du)(du)等(deng)級混凝土(tu)裂(lie)縫控制要點:合適(shi)的水(shui)灰比控制裂(lie)縫;適(shi)當(dang)的外(wai)加劑保證泵送,逐車檢測坍落度(du)(du)、擴展度(du)(du)、入模溫度(du)(du);養護過程注意保溫,一般采用導熱(re)系數低的木(mu)模。
(2)超高層泵(beng)送(song)混凝(ning)土(tu)施工(gong)時選擇料斗(dou)容(rong)量小但輸(shu)送(song)壓(ya)力大的(de)型號;泵(beng)管選擇專用高壓(ya)泵(beng)管,為(wei)節約成本(ben),低(di)層施工(gong)時可不投(tou)入高壓(ya)泵(beng)管,只采用普(pu)通泵(beng)管,待輸(shu)送(song)高度達(da)到一(yi)定高度時,再(zai)用高壓(ya)泵(beng)管替換(huan);截止(zhi)閥布置在正負零位置,防(fang)回流(liu)沖擊彎頭每30層布置一(yi)次(ci)。
(3)鋼管混凝土(tu)澆(jiao)(jiao)筑(zhu)分壓力(li)注漿和(he)塔(ta)吊吊澆(jiao)(jiao)2種方案,壓力(li)注漿施工工藝復雜,但(dan)(dan)澆(jiao)(jiao)筑(zhu)速(su)度較(jiao)快,且(qie)能保證(zheng)質(zhi)量,適合(he)截(jie)面(mian)較(jiao)小根(gen)數較(jiao)多的(de)項目;塔(ta)吊吊料斗,施工簡(jian)單,但(dan)(dan)危險(xian)性較(jiao)大,質(zhi)量難保證(zheng),占用塔(ta)吊,適合(he)單根(gen)截(jie)面(mian)較(jiao)大且(qie)根(gen)數較(jiao)少(shao)的(de)情況。
模板(ban)及支撐體(ti)系施(shi)工
(1)鋁(lv)模(mo)優點為施工速度快、成(cheng)型質量(liang)好、周轉次(ci)數多、損耗低、支撐體系簡單(dan);缺點為一次(ci)性投入大、不適(shi)合高(gao)強度等級(ji)混凝土的保(bao)溫養(yang)護(hu)裂縫控制。鋁(lv)模(mo)適(shi)合在(zai)標(biao)準(zhun)層結構簡單(dan)、標(biao)高(gao)變化不大、特(te)殊功(gong)能(neng)房間少(shao)的情況下使用,采用專業(ye)隊伍單(dan)獨分(fen)包的方式。
(2)爬(pa)模(mo)施工過程中,防(fang)高空落物(wu)為重(zhong)中之重(zhong),還應考慮(lv)操作平(ping)臺的設(she)計(ji)及(ji)安全(quan)性、爬(pa)升裝置的維修保養(yang)、爬(pa)軌防(fang)變(bian)形(xing)及(ji)數量(liang)上的富余量(liang)、變(bian)截面爬(pa)升或傾斜爬(pa)升時的爬(pa)錐(zhui)位置計(ji)算、爬(pa)錐(zhui)的預埋及(ji)掛座的拆除(chu)。
鋼結構施工(gong)
(1)鋼結構復雜構件的(de)深化設(she)計(ji)除(chu)考(kao)(kao)慮(lv)分節重(zhong)量、安裝(zhuang)(zhuang)標高、吊裝(zhuang)(zhuang)措(cuo)施、焊(han)接(jie)(jie)措(cuo)施、栓(shuan)釘及(ji)防腐涂(tu)裝(zhuang)(zhuang)由廠內施工或現場(chang)施工等問題之(zhi)外(wai),主(zhu)要(yao)應考(kao)(kao)慮(lv)鋼筋與構件交叉的(de)問題及(ji)箍筋綁扎(zha)的(de)簡化問題,在(zai)設(she)計(ji)院同意的(de)前(qian)提下可(ke)采用以下幾種方式(shi)進行(xing)節點處(chu)理:設(she)置(zhi)穿筋孔使鋼筋通過、焊(han)接(jie)(jie)套(tao)筒或連(lian)接(jie)(jie)鋼板(ban)與受(shou)力鋼筋形成(cheng)連(lian)接(jie)(jie)、在(zai)構件上焊(han)接(jie)(jie)帶孔的(de)鋼板(ban)與非(fei)受(shou)力鋼筋形成(cheng)不需施焊(han)的(de)掛鉤(gou)連(lian)接(jie)(jie)。
(2)混凝(ning)土(tu)核(he)心筒(tong)與外框鋼柱之間的變形差(cha)(cha),對于確(que)實有必要進(jin)行變形差(cha)(cha)控(kong)制(zhi)的項目,應預先(xian)模擬計算變形量(liang)(liang),然后(hou)在(zai)施工(gong)過(guo)程(cheng)中,通(tong)過(guo)實際測量(liang)(liang)來驗證預測數值的有效(xiao)性,并對后(hou)期的施工(gong)做出適量(liang)(liang)調整(zheng)。
(3)伸(shen)臂桁架(jia)及環臂桁架(jia)施工工藝及控制(zhi)要點:適當位置的(de)起拱,從下(xia)到上、從固(gu)定(ding)端到非固(gu)定(ding)端的(de)分片施工順(shun)序(xu),能(neng)起到支撐作用的(de)結構跟進(jin),減少焊接(jie)應(ying)力的(de)合理焊接(jie)順(shun)序(xu)及工藝,臨(lin)時(shi)支撐結構的(de)卸載時(shi)間(jian),空間(jian)定(ding)位測量的(de)準確性。
(4)鋼(gang)(gang)板墻(qiang)的(de)吊裝,垂直度控制(zhi)(zhi)為施工控制(zhi)(zhi)要點(dian)。由于鋼(gang)(gang)板墻(qiang)的(de)阻斷(duan)效果,使(shi)墻(qiang)體模板對拉(la)絲桿的(de)精(jing)確定位及(ji)墻(qiang)體箍筋施工都產(chan)生了(le)一定困(kun)難。
本文(wen)轉自中國建筑業協會